Hudbay approves $2.07B Copper World mine in Arizona, first output targeted H2 2029

Hudbay+1 ·
Hudbay approves $2.07B Copper World mine in Arizona, first output targeted H2 2029
  • Hudbay and Mitsubishi approved construction of Copper World, a 70%-owned (Hudbay) and 30%-owned (Mitsubishi) open-pit copper mine about 50 km southeast of Tucson, Arizona.
  • Initial growth capital is $2.07 billion, or $1.84 billion net of the Wheaton precious metals stream deposit, including about $200 million of scope changes since the 2023 PFS.
  • The DFS base case projects 102,000 tonnes of annual copper production over the first 10 years and an after-tax NPV (8%) of $1.2 billion with a 17% IRR at $5.00 per pound copper.
  • Hudbay expects consolidated annual copper production to rise to about 250,000 tonnes, roughly doubling current levels.
  • Hudbay states it has obtained all major permits needed to construct and initially operate the base project, which requires only state and local approvals.
  • Pima County Administrator Jan Lesher cited increased production and filtered-tailings use in an Oct. 21 memo, and county staff will review the feasibility study.

引述

“Copper World will be the first of the next generation of long-life, low-cost copper mines in the Americas.”— Hudbay Minerals Inc.
“increased production, the apparent use of dry stack or filtered tailings, and changes in mine facility configurations”— Jan Lesher

来源