- Optical network equipment lead times have stretched from about 3 months to 12-15 months, with some orders taking 18 months, according to a RETN report covered by The Register.
- RETN reportedly says optical equipment prices are up about 50% since the start of 2026.
- Telcos are reportedly competing with AI data centers for the same chips and parts, which is driving the supply squeeze.
- RETN advises operators building data centers away from major hubs to secure fiber carriers two to five years before opening.
Quotes
“RETN says optical equipment prices are up about 50% since the start of 2026.”